Off-Grid Solar System

JOB-2026-0167 - raised via AMC schedule 16 days ago

CompletedLow priorityQuarterly Care AMC
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Heavy soiling on lower rows

    Minor

    Dust accumulation reducing output on the two lowest rows more than the rest of the array.

    Resolved

Parts used

Consumed from van stock on this visit.

No parts consumed

Result

Generation either side of the visit.

+6 kWhper day

28 kWh before, 34 kWh after

Worth about Rs 9,180 a month at this site's tariff.

Assignment

Technician

Asif Mehmood
Details
City
Lahore
Capacity
10.0 kW
Raised
2 Aug 2026, 3:00 PM
Scheduled
4 Aug 2026, 9:00 AM
SLA due
4 Aug 2026, 3:00 PM (14 days ago)
Completed
4 Aug 2026, 9:00 AM
Services
Off-Grid Solar System
Amount
Rs 34