Lightning Protection

JOB-2026-0125 - raised via Portal 3 mo ago

CompletedLow priority
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Burnt MC4 connector

    Critical

    DC connector on string C shows arcing damage. Replaced on site and adjacent connectors re-terminated.

    Open

Parts used

Consumed from van stock on this visit.

No parts consumed

Result

Generation either side of the visit.

+11 kWhper day

75 kWh before, 86 kWh after

Worth about Rs 16,500 a month at this site's tariff.

Assignment

Technician

Naveed Iqbal
Details
City
Multan
Capacity
25.0 kW
Raised
16 May 2026, 10:00 AM
Scheduled
19 May 2026, 4:00 AM
SLA due
19 May 2026, 10:00 AM (3 mo ago)
Completed
19 May 2026, 4:00 AM
Services
Lightning Protection
Amount
Rs 45,000