All work orders
Hybrid Solar System
JOB-2026-0095 - raised via Portal 4 mo ago
CompletedLow priorityAnnual Basic AMC
Operations console
JOB-2026-0095 - raised via Portal 4 mo ago
6 of 6 steps complete
Defects recorded on site. Unresolved criticals roll up to the operations overview.
Loose structure bolt
Two mid-clamps below torque specification on the north row. Retorqued.
Resolved
Hotspot detected on string B
Thermal scan shows a cell running 27 degrees above array average. Bypass diode failure suspected.
Open
Consumed from van stock on this visit.
No parts consumed
Generation either side of the visit.
28 kWh before, 35 kWh after
Worth about Rs 11,550 a month at this site's tariff.
Technician
Danish Ali