Operations console
Prototype - no backend
Customers
Shahzad Motors - Unit 1
50.0 kW On-Grid system in Multan, commissioned 19 Aug 2020
Generation figures are modelled for the prototype from a fixed seed, so they are identical on every visit.
Operations console
50.0 kW On-Grid system in Multan, commissioned 19 Aug 2020
System health
81
Performance ratio against baseline, less open defects
Generated (30 days)
4.9 MWh
87% of expected
Modelled soiling loss
10.7%
Last cleaned 2 May 2026
Performance ratio
73.6%
Baseline 85%, target 82%
Ninety days. The dashed line is the design expectation; the gap between the lines is money.
Climbs between washes, drops sharply after rain or a clean. The dashed line is the point where a cleaning visit pays for itself.
Against the fleet target.
Unresolved defects on this site.
Inverter derating in afternoon peak
MajorUnit throttles above 46 degrees ambient. Cooling fins clogged with dust.
5 visits
| Code | Service | Status | Amount |
|---|---|---|---|
| JOB-2026-0156 | Combiner Box Repair | In progress | Rs 7.8K |
| JOB-2026-0071 | Moss & Dust Removal | Scheduled | Rs 4.2K |
| JOB-2026-0017 | Panel Replacement | Completed | Rs 18.9L |
| JOB-2026-0039 | IV Curve Testing | Completed | Rs 42.5K |
| JOB-2026-0147 | Hotspot Detection | Completed | Rs 32.5K |
8 Jun 2026
Generation figures are modelled for the prototype from a fixed seed, so they are identical on every visit.