Operations console
Prototype - no backend
Customers
Usman Tariq
7.5 kW On-Grid system in Multan, commissioned 11 Jun 2024
Generation figures are modelled for the prototype from a fixed seed, so they are identical on every visit.
Operations console
7.5 kW On-Grid system in Multan, commissioned 11 Jun 2024
System health
83
Performance ratio against baseline, less open defects
Generated (30 days)
697 kWh
83% of expected
Modelled soiling loss
16.1%
Last cleaned 21 May 2026
Performance ratio
67.3%
Baseline 81%, target 82%
Ninety days. The dashed line is the design expectation; the gap between the lines is money.
Climbs between washes, drops sharply after rain or a clean. The dashed line is the point where a cleaning visit pays for itself.
Against the fleet target.
Unresolved defects on this site.
No open findings
0 visits
No visits yet
No reports for this site
Generation figures are modelled for the prototype from a fixed seed, so they are identical on every visit.