Fuse Replacement

JOB-2026-0169 - raised via Phone 1 mo ago

CompletedLow priorityCommercial Pro AMC
Checklist

6 of 6 steps complete

Findings

Defects recorded on site. Unresolved criticals roll up to the operations overview.

  • Inverter derating in afternoon peak

    Major

    Unit throttles above 46 degrees ambient. Cooling fins clogged with dust.

    Open

Parts used

Consumed from van stock on this visit.

No parts consumed

Result

Generation either side of the visit.

+33 kWhper day

120 kWh before, 153 kWh after

Worth about Rs 48,510 a month at this site's tariff.

Assignment

Technician

Danish Ali
Details
City
Faisalabad
Capacity
32.0 kW
Raised
4 Jul 2026, 12:00 PM
Scheduled
4 Jul 2026, 4:00 PM
SLA due
4 Jul 2026, 8:00 PM (1 mo ago)
Completed
4 Jul 2026, 4:00 PM
Services
Fuse Replacement
Amount
Rs 1,900